Construction progress

House №11: A set of formwork for the 3rd floor slab is performed.

House №12: The grille is reinforced. Planning works on improvement proceed. Flooded foundation slabs.

House №13: Concreting and reinforcement of vertical elements of walls and columns, as well as concreting and reinforcement of basement stairways are performed.

Embankment: The wall is flooded, 80 monolithic heels are installed under the frame.

Civil and erection works:
31% 0%
  • House № 1
    • Works before ref. 0 - 100%
    • Frame - 40%
    • Brickwork - 0%
    • Internal equipment - 0%
  • House № 2
    • Works before ref. 0 - 50%
    • Frame - 0%
    • Brickwork - 0%
    • Internal equipment - 0%
  • House № 3
    • Works before ref. 0 - 100%
    • Frame - 77%
    • Brickwork - 0%
    • Internal equipment - 0%
Improvement:
0% 0%
Facade:
0% 0%
Utility connections:
0% 0%

Completion of construction:
Building No.1 - IV quarter 2020
Building No.2 - III quarter 2021
Building No.3 - IV quarter 2020

Sales department:
  • Kiev, Kharkov Highway,
  • 22 km (Boryspilska metro station)
  • You can order a transfer to the sales department by phone:
  • (044) 49-80-080
  • Order a call
Акційні пропозиції