Construction progress

House №1: Installation of stair and balcony railings has been completed. Laying tiles on 1-6 floors. The arrangement of stairways has begun. The installation of low-current systems in public places has been completed, and the finishing of the walls is underway. Installation of switchboard and individual heating point is carried out.

Civil and erection works:
90% 0%
    • Works before ref. 0 - 100%
    • Frame - 100%
    • Brickwork - 100%
    • Internal equipment - 56%
Facade:
90% 0%
    • Windows - 100%
    • Facade - 80%
Utility connections:
40% 0%
    • External - 0%
    • Internal - 80%
Improvement:
0% 0%

House №2: Windows are being installed on the facade. Inside the house, walls are being laid on the 4th floor and in the basement. Electricity is being installed. Elevator installation.

Civil and erection works:
69% 0%
    • Works before ref. 0 - 100%
    • Frame - 100%
    • Brickwork - 80%
    • Internal equipment - 0%
Facade:
35% 0%
    • Windows - 60%
    • Facade - 26%
Utility connections:
0% 0%
    • External - 0%
    • Internal - 0%
Improvement:
0% 0%

House №3: Arrangement of the facade on the 7th floor, work on the roof. Tiles are installed on public floors 1-6. Low-current systems are also installed in public places. Installation of switchboard and individual heating point. Mount the elevator.

Civil and erection works:
89% 0%
    • Works before ref. 0 - 100%
    • Frame - 100%
    • Brickwork - 100%
    • Internal equipment - 56%
Facade:
90% 0%
    • Windows - 100%
    • Facade - 80%
Utility connections:
22% 0%
    • External - 0%
    • Internal - 80%
Improvement:
0% 0%

House №4: Windows are being installed.

Civil and erection works:
68% 0%
    • Works before ref. 0 - 100%
    • Frame - 100%
    • Brickwork - 71%
    • Internal equipment - 0%
Facade:
23% 0%
    • Windows - 45%
    • Facade - 1%
Utility connections:
0% 0%
    • External - 0%
    • Internal - 0%
Improvement:
0% 0%

House №5: The walls are being laid on 2-6 floors.

Civil and erection works:
57% 0%
    • Works before ref. 0 - 100%
    • Frame - 95%
    • Brickwork - 31%
    • Internal equipment - 0%
Facade:
0% 0%
    • Windows - 0%
    • Facade - 0%
Utility connections:
0% 0%
    • External - 0%
    • Internal - 0%
Improvement:
0% 0%

House №6: Concreting of vertical and horizontal elements continues on the 3rd floor.

Civil and erection works:
39% 0%
    • Works before ref. 0 - 94%
    • Frame - 61%
    • Brickwork - 0%
    • Internal equipment - 0%
Facade:
0% 0%
    • Windows - 0%
    • Facade - 0%
Utility connections:
0% 0%
    • External - 0%
    • Internal - 0%
Improvement:
0% 0%

House №7: From 4 to 6 floors is masonry.

Civil and erection works:
40% 0%
    • Works before ref. 0 - 100%
    • Frame - 95%
    • Brickwork - 55%
    • Internal equipment - 0%
Facade:
0% 0%
    • Windows - 0%
    • Facade - 0%
Utility connections:
0% 0%
    • External - 0%
    • Internal - 0%
Improvement:
0% 0%

House №8: Concreting of vertical elements of the 3rd floor is performed.

Civil and erection works:
25% 0%
    • Works before ref. 0 - 89%
    • Frame - 54%
    • Brickwork - 0%
    • Internal equipment - 0%
Facade:
0% 0%
    • Windows - 0%
    • Facade - 0%
Utility connections:
0% 0%
    • External - 0%
    • Internal - 0%
Improvement:
0% 0%

House №10: On 3-6 floors there is a laying of walls.

Civil and erection works:
40% 0%
    • Works before ref. 0 - 98%
    • Frame - 93%
    • Brickwork - 20%
    • Internal equipment - 0%
Facade:
0% 0%
    • Windows - 0%
    • Facade - 0%
Utility connections:
0% 0%
    • External - 0%
    • Internal - 0%
Improvement:
0% 0%

House №12: A soft roof is being installed.

Civil and erection works:
54% 0%
    • Works before ref. 0 - 100%
    • Frame - 98%
    • Brickwork - 17%
    • Internal equipment - 0%
Facade:
0% 0%
    • Windows - 0%
    • Facade - 0%
Utility connections:
0% 0%
    • External - 0%
    • Internal - 0%
Improvement:
0% 0%

Quay: Tracks are being installed.

Completion of construction:
Building No.1 - I quarter 2022
Building No.2 - III quarter 2022
Building No.3 - I quarter 2022
Building No.4 - IV quarter 2022
Building No.5 - II quarter 2022
Building No.6 - IV quarter 2022
Building No.7 - III quarter 2022
Building No.8 - II quarter 2023
Building No.9 - II quarter 2024
Building No.10 - II quarter 2023
Building No.12 - III quarter 2022

Завантажити ще
Sales department:
  • Kiev, Kharkov Highway,
  • 22 km (Boryspilska metro station)
  • You can order a transfer to the sales department by phone:
  • (044) 49-80-080
  • Order a call
Акційні пропозиції