Construction progress

House №1: Installation of internal heating, ventilation, plumbing, sewerage and electricity. Installation of aluminum window constructions of the 1st floor continues. Roof waterproofing works are underway. Applying decor on the facade.

Civil and erection works:
73% 0%
    • Works before ref. 0 - 95%
    • Frame - 100%
    • Brickwork - 95%
    • Internal equipment - 0%
Facade:
70% 0%
    • Windows - 80%
    • Facade - 60%
Utility connections:
5% 0%
    • External - 0%
    • Internal - 10%
Improvement:
0% 0%

House №2: Laying works from the gas block. Installation of window constructions.

Civil and erection works:
68% 0%
    • Works before ref. 0 - 95%
    • Frame - 95%
    • Brickwork - 80%
    • Internal equipment - 0%
Facade:
0% 0%
    • Windows - 0%
    • Facade - 0%
Utility connections:
0% 0%
    • External - 0%
    • Internal - 0%
Improvement:
0% 0%

House №3: Installation of a profiled sheet on a roof proceeds. Installation of internal networks of heating, ventilation, water supply, sewerage, electricity is performed. Applying decor on the facade.

Civil and erection works:
73% 0%
    • Works before ref. 0 - 95%
    • Frame - 100%
    • Brickwork - 95%
    • Internal equipment - 0%
Facade:
70% 0%
    • Windows - 80%
    • Facade - 60%
Utility connections:
5% 0%
    • External - 0%
    • Internal - 10%
Improvement:
0% 0%

House №4: The monolith of the 6th floor is being installed. Masonry work on the gas block on 2-4 floors.

Civil and erection works:
40% 0%
    • Works before ref. 0 - 95%
    • Frame - 65%
    • Brickwork - 0%
    • Internal equipment - 0%
Facade:
0% 0%
    • Windows - 0%
    • Facade - 0%
Utility connections:
0% 0%
    • External - 0%
    • Internal - 0%
Improvement:
0% 0%

House №5: Basement vertical set.

Civil and erection works:
0% 0%
    • Works before ref. 0 - 0%
    • Frame - 0%
    • Brickwork - 0%
    • Internal equipment - 0%
Facade:
0% 0%
    • Windows - 0%
    • Facade - 0%
Utility connections:
0% 0%
    • External - 0%
    • Internal - 0%
Improvement:
0% 0%

House №7: Concrete preparation works are underway.

Civil and erection works:
0% 0%
    • Works before ref. 0 - 0%
    • Frame - 0%
    • Brickwork - 0%
    • Internal equipment - 0%
Facade:
0% 0%
    • Windows - 0%
    • Facade - 0%
Utility connections:
0% 0%
    • External - 0%
    • Internal - 0%
Improvement:
0% 0%

Completion of construction:
Building No.1 - II quarter 2021
Building No.2 - III quarter 2021
Building No.3 - II quarter 2021
Building No.4 - III quarter 2021
Building No.5 - II quarter 2022
Building No.6 - IV quarter 2022
Building No.7 - III quarter 2022

Sales department:
  • Kiev, Kharkov Highway,
  • 22 km (Boryspilska metro station)
  • You can order a transfer to the sales department by phone:
  • (044) 49-80-080
  • Order a call
Акційні пропозиції