Construction progress

Houses № 1 and № 3: House № 1 floods the floor slab at -0,100… -0,700. In the house № 3 works are done on the installation of vertical formwork at the mark of -2,600.

House № 2: Grid reinforcement is in progress - 60% readiness. Planning work on improvement is ongoing. The foundation slabs are flooded.

Civil and erection works:
18% 0%
  • House № 1
    • Works before ref. 0 - 100%
    • Frame - 0%
    • Brickwork - 0%
    • Internal equipment - 0%
  • House № 2
    • Works before ref. 0 - 50%
    • Frame - 0%
    • Brickwork - 0%
    • Internal equipment - 0%
  • House № 3
    • Works before ref. 0 - 60%
    • Frame - 0%
    • Brickwork - 0%
    • Internal equipment - 0%
Improvement:
0% 0%
Facade:
0% 0%
Utility connections:
0% 0%

Completion of construction:
Building No.1 - IV quarter 2020
Building No.2 - IV quarter 2020
Building No.3 - III quarter 2020