Construction progress

House №1: Glazing from the 2nd to the 6th floor is completed.

House №2: Pour the plate on the 6th floor (readiness 60%). Masonry works of external walls to the 4th floor are carried out.

House №3: The roof frame and glazing work have been completed.

House №4: Preparations are underway for the installation of a floor slab on the 1st floor. Set of formwork under the vertical of the 2nd floor.

Civil and erection works:
53% 0%
  • House № 1
    • Works before ref. 0 - 100%
    • Frame - 100%
    • Brickwork - 100%
    • Internal equipment - 0%
    • House № 2
    • Works before ref. 0 - 95%
    • Frame - 40%
    • Brickwork - 15%
    • Internal equipment - 0%
  • House № 3
    • Works before ref. 0 - 100%
    • Frame - 100%
    • Brickwork - 95%
    • Internal equipment - 0%
  • House № 4
    • Works before ref. 0 - 100%
    • Frame - 15%
    • Brickwork - 0%
    • Internal equipment - 0%
Improvement:
0% 0%
Facade:
0% 0%
Utility connections:
0% 0%

Completion of construction:
Building No.1 - II quarter 2021
Building No.2 - III quarter 2021
Building No.3 - II quarter 2021
Building No.4 - III quarter 2021
Building No.5 - II quarter 2022
Building No.6 - IV quarter 2022
Building No.7 - III quarter 2022

Sales department:
  • Kiev, Kharkov Highway,
  • 22 km (Boryspilska metro station)
  • You can order a transfer to the sales department by phone:
  • (044) 49-80-080
  • Order a call
Акційні пропозиції