Construction progress
House №1: Finishing works are underway in public places, tiles are being laid on 2-6 floors, low-current systems, external networks, water supply and sewerage, heating and ventilation are being installed.
-
- Works before ref. 0 - 100%
- Frame - 100%
- Brickwork - 100%
- Internal equipment - 86%
-
- Windows - 100%
- Facade - 80%
-
- External - 0%
- Internal - 92%
House №2: Masonry of the 4th and 6th floors, installation of translucent window constructions is underway.
-
- Works before ref. 0 - 100%
- Frame - 100%
- Brickwork - 80%
- Internal equipment - 0%
-
- Windows - 60%
- Facade - 27%
-
- External - 0%
- Internal - 0%
House №3: Finishing works are carried out in public places, tiles are arranged on 2-6 floors, low-current systems, external networks, water supply and sewerage, heating and ventilation are installed.
-
- Works before ref. 0 - 100%
- Frame - 100%
- Brickwork - 100%
- Internal equipment - 62%
-
- Windows - 100%
- Facade - 80%
-
- External - 0%
- Internal - 84%
House №4: Windows are being installed and walls are being laid.
-
- Works before ref. 0 - 100%
- Frame - 100%
- Brickwork - 71%
- Internal equipment - 0%
-
- Windows - 47%
- Facade - 1%
-
- External - 0%
- Internal - 0%
House №5: The walls are being laid on 2-6 floors.
-
- Works before ref. 0 - 100%
- Frame - 95%
- Brickwork - 35%
- Internal equipment - 0%
-
- Windows - 0%
- Facade - 0%
-
- External - 0%
- Internal - 0%
House №6: Installation of ventilation units on the 2nd and 3rd floors is carried out.
-
- Works before ref. 0 - 100%
- Frame - 71%
- Brickwork - 0%
- Internal equipment - 0%
-
- Windows - 0%
- Facade - 0%
-
- External - 0%
- Internal - 0%
House №7: From 4 to 6 floors is masonry.
-
- Works before ref. 0 - 100%
- Frame - 95%
- Brickwork - 56%
- Internal equipment - 0%
-
- Windows - 0%
- Facade - 0%
-
- External - 0%
- Internal - 0%
House №8: Concreting of vertical elements of the 3rd floor is performed.
-
- Works before ref. 0 - 89%
- Frame - 54%
- Brickwork - 0%
- Internal equipment - 0%
-
- Windows - 0%
- Facade - 0%
-
- External - 0%
- Internal - 0%
House №9: The site is being prepared for the foundation.
-
- Works before ref. 0 - 0%
- Frame - 0%
- Brickwork - 0%
- Internal equipment - 0%
-
- Windows - 0%
- Facade - 0%
-
- External - 0%
- Internal - 0%
House №10: The walls of the 4th floor are being laid.
-
- Works before ref. 0 - 98%
- Frame - 93%
- Brickwork - 20%
- Internal equipment - 0%
-
- Windows - 0%
- Facade - 0%
-
- External - 0%
- Internal - 0%
House №12: A soft roof is being installed.
-
- Works before ref. 0 - 100%
- Frame - 98%
- Brickwork - 19%
- Internal equipment - 0%
-
- Windows - 0%
- Facade - 0%
-
- External - 0%
- Internal - 0%
Quay: Tracks are being installed.