Close Form Button
Close

Order call

Construction progress

House №1: The filling of the arm belt is completed.

House №2: A set of formwork and reinforcement is performed on the 3rd and 4th floors.

House №3: Loading of the gas block on floors. Laying of interroom partitions proceeds.

House №4: Set of vertical basement frames.

Civil and erection works:
37% 0%
  • House № 1
    • Works before ref. 0 - 100%
    • Frame - 65%
    • Brickwork - 0%
    • Internal equipment - 0%
  • House № 2
    • Works before ref. 0 - 50%
    • Frame - 1%
    • Brickwork - 0%
    • Internal equipment - 0%
  • House № 3
    • Works before ref. 0 - 100%
    • Frame - 95%
    • Brickwork - 27%
    • Internal equipment - 0%
Improvement:
0% 0%
Facade:
0% 0%
Utility connections:
0% 0%

Completion of construction:
Building No.1 - IV quarter 2020
Building No.2 - III quarter 2021
Building No.3 - IV quarter 2020
Building No.4 - III quarter 2021
Building No.5 - II quarter 2022

Sales department:
  • Kiev, Kharkov Highway,
  • 22 km (Boryspilska metro station)
  • You can order a transfer to the sales department by phone:
  • (044) 49-80-080
  • Order a call
Акційні пропозиції