Construction progress

House №1: Roof insulation continues - readiness 80%. Ventilation is 70% complete.

Civil and erection works:
75% 0%
    • Works before ref. 0 - 100%
    • Frame - 100%
    • Brickwork - 95%
    • Internal equipment - 5%
Facade:
90% 0%
    • Windows - 100%
    • Facade - 80%
Utility connections:
40% 0%
    • External - 0%
    • Internal - 80%
Improvement:
0% 0%

House №2: The walls of the 1st and 6th floors are being laid. Windows are mounted on the 6th floor.

Civil and erection works:
68% 0%
    • Works before ref. 0 - 95%
    • Frame - 95%
    • Brickwork - 80%
    • Internal equipment - 0%
Facade:
15% 0%
    • Windows - 60%
    • Facade - 0%
Utility connections:
0% 0%
    • External - 0%
    • Internal - 0%
Improvement:
0% 0%

House №3: On the 6th floor they finished heating, water supply was made. On the 2nd and 3rd floors poured screed. 80% of the parapet seam was installed, 20% of the roof was insulated.

Civil and erection works:
73% 0%
    • Works before ref. 0 - 95%
    • Frame - 100%
    • Brickwork - 95%
    • Internal equipment - 0%
Facade:
90% 0%
    • Windows - 100%
    • Facade - 80%
Utility connections:
20% 0%
    • External - 0%
    • Internal - 80%
Improvement:
0% 0%

House №4: Masonry work continues on the 1st floor - readiness 80%. Readiness of an armopoyas - 15%. Concrete covers under the marches.

Civil and erection works:
63% 0%
    • Works before ref. 0 - 95%
    • Frame - 95%
    • Brickwork - 60%
    • Internal equipment - 0%
Facade:
0% 0%
    • Windows - 0%
    • Facade - 0%
Utility connections:
0% 0%
    • External - 0%
    • Internal - 0%
Improvement:
0% 0%

House №5: The vertical device of the 5th floor is being installed. Installation of vent blocks is ready for 40%.

Civil and erection works:
26% 0%
    • Works before ref. 0 - 80%
    • Frame - 25%
    • Brickwork - 0%
    • Internal equipment - 0%
Facade:
0% 0%
    • Windows - 0%
    • Facade - 0%
Utility connections:
0% 0%
    • External - 0%
    • Internal - 0%
Improvement:
0% 0%

House №6: Reinforcement of the plinth vertical is made by 20%.

Civil and erection works:
3% 0%
    • Works before ref. 0 - 20%
    • Frame - 0%
    • Brickwork - 0%
    • Internal equipment - 0%
Facade:
0% 0%
    • Windows - 0%
    • Facade - 0%
Utility connections:
0% 0%
    • External - 0%
    • Internal - 0%
Improvement:
0% 0%

House №7: Installation of vent blocks proceeds - readiness of 40%. The readiness of the vertical 4th floor is 20%.

Civil and erection works:
25% 0%
    • Works before ref. 0 - 25%
    • Frame - 20%
    • Brickwork - 0%
    • Internal equipment - 0%
Facade:
0% 0%
    • Windows - 0%
    • Facade - 0%
Utility connections:
0% 0%
    • External - 0%
    • Internal - 0%
Improvement:
0% 0%

House №8: Flooded 1\3 plates of the grille.

Civil and erection works:
0% 0%
    • Works before ref. 0 - 0%
    • Frame - 0%
    • Brickwork - 0%
    • Internal equipment - 0%
Facade:
0% 0%
    • Windows - 0%
    • Facade - 0%
Utility connections:
0% 0%
    • External - 0%
    • Internal - 0%
Improvement:
0% 0%

House №10: The vertical of the 4th floor is made by 95%.

Civil and erection works:
0% 0%
    • Works before ref. 0 - 0%
    • Frame - 0%
    • Brickwork - 0%
    • Internal equipment - 0%
Facade:
0% 0%
    • Windows - 0%
    • Facade - 0%
Utility connections:
0% 0%
    • External - 0%
    • Internal - 0%
Improvement:
0% 0%

Completion of construction:
Building No.1 - IV quarter 2021
Building No.2 - IV quarter 2021
Building No.3 - IV quarter 2021
Building No.4 - IV quarter 2021
Building No.5 - II quarter 2022
Building No.6 - IV quarter 2022
Building No.7 - III quarter 2022
Building No.8 - II quarter 2023

Sales department:
  • Kiev, Kharkov Highway,
  • 22 km (Boryspilska metro station)
  • You can order a transfer to the sales department by phone:
  • (044) 49-80-080
  • Order a call
Акційні пропозиції