Construction progress

House №1: Finishing works are underway in public places, tiles are being laid on 2-6 floors, low-current systems, external networks, water supply and sewerage, heating and ventilation are being installed.

Civil and erection works:
97.5% 0%
    • Works before ref. 0 - 100%
    • Frame - 100%
    • Brickwork - 100%
    • Internal equipment - 90%
Facade:
90% 0%
    • Windows - 100%
    • Facade - 80%
Utility connections:
90% 0%
    • External - 90%
    • Internal - 90%
Improvement:
0% 0%

House №2: Masonry of the 4th and 6th floors, installation of translucent window constructions is underway.

Civil and erection works:
75% 0%
    • Works before ref. 0 - 100%
    • Frame - 100%
    • Brickwork - 100%
    • Internal equipment - 0%
Facade:
65% 0%
    • Windows - 80%
    • Facade - 50%
Utility connections:
30% 0%
    • External - 50%
    • Internal - 10%
Improvement:
0% 0%

House №3: Finishing works are carried out in public places, tiles are arranged on 2-6 floors, low-current systems, external networks, water supply and sewerage, heating and ventilation are installed.

Civil and erection works:
98.75% 0%
    • Works before ref. 0 - 100%
    • Frame - 100%
    • Brickwork - 100%
    • Internal equipment - 95%
Facade:
92.5% 0%
    • Windows - 100%
    • Facade - 85%
Utility connections:
90% 0%
    • External - 90%
    • Internal - 90%
Improvement:
0% 0%

House №4: Windows are being installed and walls are being laid.

Civil and erection works:
72.5% 0%
    • Works before ref. 0 - 100%
    • Frame - 100%
    • Brickwork - 90%
    • Internal equipment - 0%
Facade:
40% 0%
    • Windows - 80%
    • Facade - 1%
Utility connections:
30% 0%
    • External - 50%
    • Internal - 10%
Improvement:
0% 0%

House №5: The walls are being laid on 2-6 floors.

Civil and erection works:
72.5% 0%
    • Works before ref. 0 - 100%
    • Frame - 100%
    • Brickwork - 90%
    • Internal equipment - 0%
Facade:
0% 0%
    • Windows - 0%
    • Facade - 0%
Utility connections:
10% 0%
    • External - 020%
    • Internal - 0%
Improvement:
0% 0%

House №6: Installation of ventilation units on the 2nd and 3rd floors is carried out.

Civil and erection works:
37.5% 0%
    • Works before ref. 0 - 100%
    • Frame - 50%
    • Brickwork - 0%
    • Internal equipment - 0%
Facade:
0% 0%
    • Windows - 0%
    • Facade - 0%
Utility connections:
0% 0%
    • External - 0%
    • Internal - 0%
Improvement:
0% 0%

House №7: From 4 to 6 floors is masonry.

Civil and erection works:
72.5% 0%
    • Works before ref. 0 - 100%
    • Frame - 100%
    • Brickwork - 90%
    • Internal equipment - 0%
Facade:
0% 0%
    • Windows - 0%
    • Facade - 0%
Utility connections:
10% 0%
    • External - 20%
    • Internal - 0%
Improvement:
0% 0%

House №8: Concreting of vertical elements of the 3rd floor is performed.

Civil and erection works:
37.5% 0%
    • Works before ref. 0 - 100%
    • Frame - 50%
    • Brickwork - 0%
    • Internal equipment - 0%
Facade:
0% 0%
    • Windows - 0%
    • Facade - 0%
Utility connections:
0% 0%
    • External - 0%
    • Internal - 0%
Improvement:
0% 0%

House №9: The site is being prepared for the foundation.

Civil and erection works:
3.75% 0%
    • Works before ref. 0 - 15%
    • Frame - 0%
    • Brickwork - 0%
    • Internal equipment - 0%
Facade:
0% 0%
    • Windows - 0%
    • Facade - 0%
Utility connections:
0% 0%
    • External - 0%
    • Internal - 0%
Improvement:
0% 0%

House №10: The walls of the 4th floor are being laid.

Civil and erection works:
70% 0%
    • Works before ref. 0 - 100%
    • Frame - 100%
    • Brickwork - 80%
    • Internal equipment - 0%
Facade:
0% 0%
    • Windows - 0%
    • Facade - 0%
Utility connections:
0% 0%
    • External - 0%
    • Internal - 0%
Improvement:
0% 0%

House №12: A soft roof is being installed.

Civil and erection works:
55% 0%
    • Works before ref. 0 - 100%
    • Frame - 100%
    • Brickwork - 20%
    • Internal equipment - 0%
Facade:
0% 0%
    • Windows - 0%
    • Facade - 0%
Utility connections:
0% 0%
    • External - 0%
    • Internal - 0%
Improvement:
0% 0%

Quay: Tracks are being installed.

Completion of construction:
Building No.1 - Constructoin is completed
Building No.2 - II quarter 2024
Building No.3 - Constructoin is completed
Building No.4 - II quarter 2024
Building No.5 - IV quarter 2024
Building No.6 - IV quarter 2024
Building No.7 - IV quarter 2024
Building No.8 - IV quarter 2024
Building No.9 - IV quarter 2025
Building No.10 - I quarter 2025
Building No.12 - I quarter 2025

Загрузить еще
Sales department:
  • Kiev, Kharkov Highway,
  • 22 km (Boryspilska metro station)
  • You can order a transfer to the sales department by phone:
  • (044) 49-80-080
  • Order a call
Акційні пропозиції